Submit Your Work
What You Turn In
- Your team's scope statement with the owner's yes fill in on the hub
- Deliverables by name; at least three out lines the owner would have assumed were in; each assumption with 'if false'; who signs and the changes line; every line from the brief or the canvas; the owner's yes saved
- Your team's risk list, dated twice fill in on the hub
- Five risks with likelihood and impact; one star for the one that would sink it, with an action already started, an owner and a date; a second date with at least one risk changed, closed or added
- A change request, signed or declined fill in on the hub
- A real ask; what is added; the price from the floor; what it does to the date; two options, no recommendation; the owner's signed yes or written no. If no ask has come yet, say so
- Your escalation note, initialled by a coach
- The four parts said on a fault card within two minutes: what happened, what it means, two options, what I need by when; or the real one with the owner's reply saved
- The tool's draft with your cuts
- Invented politeness, urgency and any discount cut; the price and the words sent are yours; labelled AI-assisted, directed by me
Stuck, or want to check your thinking? Paste this card into your own AI and ask it to question you, not answer for you.
How
- Asha, before the CAP4 handover (week 8 Thursday).
Done when
- Team's scope statement with the owner's yes: Deliverables by name; three or more out lines the owner would assume; assumptions with 'if false'; who signs; traces to brief or canvas; yes saved
- Team's risk list, two dates: Five risks with likelihood and impact; one star with a started action, owner and date; second dated update with a change
- Change request, signed or declined: Real ask; what is added; floor price; date effect; two options without recommendation; owner's signed yes or written no, or a note that no ask has come
- Escalation note, coach-initialled: Four parts on a fault card within two minutes with the observer's ticks; or run for real with the owner's reply
- Tool draft with cuts: Invented politeness, urgency and discount cut; price and wording the trainee's own; labelled AI-assisted
Counts toward: the CC10 badge, 1 to 3 stars · the client's file and the capstone folder · attendance for the briefing and the capstone SGL blocks · LP (Lion Points) for accepted badge work.
Fill in the worksheet Submit work for CC10